On September 22, state bridge inspectors started their routine check of the westbound Veterans Memorial Bridge. Hudson's Elvis Dhima, the town's development services director and town engineer, later described that day to the Board of Selectmen. About an hour into the inspection he got a call, and in his words there was "a lot of panic." One of the bridge's four steel girders had a crack. The photos weren't clear enough for him, so he went up in a bucket truck to look for himself. "It's a good-sized crack," he told the board, "and it needs to be addressed." That account is in the September 22 Board of Selectmen minutes.
The bridge work that has had the Hudson-Nashua crossing torn up for two years covered the deck, the surface you drive on. The steel girders under it have had no rehab work yet. Dhima told the board the bridge went in in 1970, though a 2024 Nashua Telegraph article dates Veterans Memorial to 1973. This crack is the first problem in that steel to be found and fixed.
What two years of bridge work actually covered
The twin bridges carry Route 111 over the Merrimack. Hudson and Nashua own and maintain them together. Eastbound traffic uses the Taylor Falls Bridge and westbound uses Veterans Memorial, and the two spans carry about 37,000 vehicles a day between them, according to ENR's September 30 report.
Dhima went over the recent work at the September 22 meeting. Almost 95 percent of it, he said, was asphalt and the concrete deck. Some went to guardrails, and the state paid for new lights. "There was no work done to the girders," he said. "Girders are basically the metal beams carrying the deck."
The reported price of that project has gone up over time. In March 2024, the Nashua Telegraph put it at $2,534,100. Federal money covered 80 percent, and Nashua and Hudson split the $506,820 local share. The plan listed pavement removal, concrete repair, a waterproofing membrane, new expansion joints and new guardrails, and it specifically left out a full deck replacement. ENR's September 2026 article called it a "more than $3-million" deck rehab that is wrapping up and set to finish in December. The two sources don't explain the gap between those figures. What they agree on is the scope. Everything in it sits on top of the beams.
How a cracked girder gets fixed
NHDOT checks the bridges every two years at its own expense. In exchange, the town helps with the detour. ENR reported that this inspection found a crack about 30 inches long, roughly 150 feet from the abutment on the Hudson side. Wright-Pierce, the town's structural engineering consultant, has finished a repair design priced at $38,000. According to the Wright-Pierce document ENR cited, the repair goes like this:
- Clean the damaged area of the beam.
- Run red dye penetrant tests on both sides of the beam.
- Drill with magnetic-base equipment.
- Install web plates on both sides of the I-girder.
- Fasten the plates with high-strength structural bolts.
The plates are unusually big because of the crack's shape. Dhima explained it to ENR:
"The job is basically a steel plate repair... The plate will be installed on both side of the I-beam."
Each plate measures 6 feet by 3 feet 3 inches. The plates that join two I-beams are usually 12 to 18 inches long. ENR reports these need the extra size because the crack is "a weird shape," not a clean right angle, and the plate has to cover it fully on both sides.
The estimate has come down since the first week. On September 22, Dhima told selectmen he expected the repair to cost $50,000 to $75,000. He asked the board for authority to spend up to $100,000 from emergency funds so he wouldn't have to come back for more. Eight days later, ENR reported the finished design at $38,000. No one knows yet what caused the crack.
Why the town closed one lane and left the rest open
The cracked girder runs along the upstream edge of the bridge, right under the sidewalk. Dhima told the board that one of the four girders needs work and the other three are fine. That's why the town closed one lane and kept the rest of the bridge open. The Hudson Times reported the same reasoning. Officials decided a full closure wasn't needed "at this time."
The lane is closed off with large barrels instead of Jersey barriers. Dhima said the town didn't want to put extra weight on the bridge. The sidewalk is still open. When a selectman asked about it, Dhima said the town couldn't enforce a sidewalk closure, and he didn't think foot traffic was the issue. He pointed to the bridge's age instead.
The detour runs over the busiest crossing
The town's posted detour, as reported in the Nashua Telegraph, sends drivers down Lowell Road to the Circumferential Highway westbound ramp and across the Sagamore Bridge. The Sagamore was already the busiest crossing before the closure. Traffic counts in the Nashua Regional Planning Commission's transportation chapter show 44,268 vehicles a day on the Sagamore in 2025, compared with 31,417 on Taylor Falls. The same chapter lists the twin-bridge area and its connecting streets on both banks as a long-running congestion spot with serious intersection capacity problems.
So the detour sends extra traffic onto a bridge that already carried about 13,000 more vehicles a day than Taylor Falls in 2025. No one has published measurements of how the closure has changed backups on Central Street, Derry Street or Lowell Road. The Hudson Times did report that officials expected more congestion at morning and afternoon commute times and advised drivers to leave extra time.
Where each piece stands as of October 12
Hudson isn't the only place dealing with this. ENR noted that Manchester closed its Queen City Bridge the day before, also after a routine NHDOT inspection. For Hudson's crossing, here is the latest public information on each piece of work:
| Work | Latest reported status | As of |
|---|---|---|
| Westbound lane closure | Closed since September 22; officials estimated four to six weeks | Sept. 30 |
| Girder crack repair | $38,000 design done; town expected E.D. Swett under contract by October 2; about three weeks of field work with six workers | Sept. 30 |
| Twin-bridge deck rehab | Deck, lights and rails nearly done; completion set for December | Sept. 30 |
| Phase two rehabilitation | About $2.4 million planned by NHDOT, per the town; state confirmation pending | Sept. 30 |
The contract date, the field schedule, the December finish and the phase-two money were all forecasts when ENR reported them. ENR described E.D. Swett as a Concord-based, employee-owned bridge contractor. ENR's September 30 report doesn't confirm that the contract was signed or that crews had started, and the Hudson Times article listed October 3 repeats the original four-to-six-week outlook without a revised date. The town's closure notice was posted September 22 and hasn't been updated since. The agenda for the October 13 Board of Selectmen meeting doesn't list the bridge as a business item.
If you count four to six weeks from September 22, the estimate puts a reopening somewhere between about October 20 and November 3. That window is just the officials' early estimate, and the Hudson Times noted that the timing depends on what the inspection and repair turn up.
The steel underneath is the next project
When Dhima explained why the sidewalk didn't matter, he made a bigger point about the girders. "I think the girders will have to be something that we need to strip down and paint because there's some rust going on," he told selectmen. He said the Nashua side is the same, but the town "can only do so much at a time," so the deck had to come first. He also said the town will eventually need to work with Nashua again, as it did on the deck.
That next round is already being discussed. Dhima told ENR there are four more beams that extend into Nashua, and that the state plans to add the bridges to the NHDOT Ten Year Plan. Under that plan, he said, the state would pay 80 percent of the extra costs and Hudson would put up a 10 percent match. He said NHDOT is planning about $2.4 million for phase two and that he expected a letter with the project name and number within a week or two. NHDOT didn't answer ENR's questions about it.
Dhima also talked about the bridge's age. The 56-year-old bridge has a life expectancy of 74 to 100 years, he told ENR, "but is showing some wear and tear." His description of where things stand:
"Everything is great and then we hit the 50-year mark and folks say because you haven't dealt with the bridge in the past 50 years, will you fix the bridge?"
The plates bolted on this fall fix one beam. Under the town's description of phase two, the rest of the original steel under both bridges comes after that, with the work again shared with Nashua and most of it paid for by the state.
If you're weighing a move on either side of the river and the Route 111 crossing matters to your commute, Michelle Daley follows these projects closely and can give you a clear picture of the area before you decide. Request your free home valuation & staging consultation.